CASE OF JGK STATYBA LTD v. LITHUANIA

Application no. 3330/12 · Delivered 2015-01-27 · ECLI:CE:ECHR:2015:0127JUD000333012 · Languages: EN · EN · LT

Application no.
3330/12
Delivered
2015-01-27
Respondent State
LTU
Conclusion
Pecuniary damage - award (Article 41 - Pecuniary damage;Just satisfaction)
Convention articles
41
Original
HUDOC ↗
PresidentGuido RaimondiJudgeIşıl KarakaşJudgeDragoljub PopovićJudgeAndrás SajóJudgePaulo Pinto de AlbuquerqueJudgeHelen KellerJudgeEgidijus KūrisRegistrarStanley Naismith
Government AgentElvyra Baltutytė
Summary
Preparing…

FORMER SECOND SECTION

CASE OF JGK STATYBA LTD v. LITHUANIA

(Application no. 3330/12)

JUDGMENT

(Just satisfaction)

STRASBOURG

27 January 2015

FINAL

27/04/2015

This judgment has become final under Article 44 § 2 of the Convention. It may be subject to editorial revision.

In the case of JGK Statyba Ltd v. Lithuania,

The European Court of Human Rights (Second Section), sitting as a Chamber composed of:

Guido Raimondi, President,

Işıl Karakaş,

Dragoljub Popović,

András Sajó,

Paulo Pinto de Albuquerque,

Helen Keller,

Egidijus Kūris, judges,

and Stanley Naismith, Section Registrar,

Having deliberated in private on 16 December 2014,

Delivers the following judgment, which was adopted on that date:

PROCEDURE

THE LAW

“If the Court finds that there has been a violation of the Convention or the Protocols thereto, and if the internal law of the High Contracting Party concerned allows only partial reparation to be made, the Court shall, if necessary, afford just satisfaction to the injured party.”

A. Damage

B. Costs and expenses

C. Default interest

FOR THESE REASONS, THE COURT, UNANIMOUSLY,

1. Holds

(a) that the respondent State is to pay the applicant company, within three months from the date on which the judgment becomes final in accordance with Article 44 § 2 of the Convention, the following amounts:

(i) EUR 70,000 (seventy thousand euros), plus any tax that may be chargeable, in respect of pecuniary damage;

(ii) EUR 10,000 (ten thousand euros), plus any tax that may be chargeable to the applicant company, in respect of costs and expenses;

(b) that from the expiry of the above-mentioned three months until settlement simple interest shall be payable on the above amounts at a rate equal to the marginal lending rate of the European Central Bank during the default period plus three percentage points;

Done in English, and notified in writing on 27 January 2015, pursuant to Rule 77 §§ 2 and 3 of the Rules of Court.

Stanley Naismith Guido Raimondi

Registrar President

Text from our archive (European Court of Human Rights, HUDOC). © Council of Europe / European Court of Human Rights. Reuse permitted with attribution; the Court's translations into languages other than English and French are not authoritative.