Judgment of the Court (Third Chamber) of 14 February 2008.

Delivered 2008-02-14 · ECLI:EU:C:2008:91 · Court of Justice · Languages: LT · EN · IT · SV · PL · LV · ET · SL

Case
C-450/06
Court
Court of Justice
Date
2008-02-14
Parties
Varec SA v Belgian State.
ECLI
ECLI:EU:C:2008:91
Original
EUR-Lex ↗
JudgeA. RosasJudge · rapporteurJ.N. Cunha RodriguesJudgeJ. KlučkaJudgeP. LindhJudgeA. ArabadjievAdvocate GeneralE. SharpstonRegistrarR. Grass
Summary
Preparing…

Parties

Grounds

Operative part

Parties

In Case C‑450/06,

REFERENCE for a preliminary ruling under Article 234 EC from the Conseil d’État (Council of State) (Belgium), made by decision of 24 October 2006, received at the Court on 6 November 2006, in the proceedings

Varec SA

v

État belge,

intervener:

Diehl Remscheid GmbH & Co.,

THE COURT (Third Chamber),

composed of A. Rosas, President of Chamber, J.N. Cunha Rodrigues (Rapporteur), J. Klučka, P. Lindh and A. Arabadjiev, Judges,

Advocate General: E. Sharpston,

Registrar: R. Grass,

having regard to the written procedure,

after considering the observations submitted on behalf of:

Judgment

Grounds

Legal context

Community legislation

‘The Member States shall take the measures necessary to ensure that, as regards contract award procedures falling within the scope of Directives 71/305/EEC, 77/62/EEC, and 92/50/EEC …, decisions taken by the contracting authorities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in the following Articles and, in particular, Article 2(7) on the grounds that such decisions have infringed Community law in the field of public procurement or national rules implementing that law.’
‘Where bodies responsible for review procedures are not judicial in character, written reasons for their decisions shall always be given. Furthermore, in such a case, provision must be made to guarantee procedures whereby any allegedly illegal measure taken by the review body or any alleged defect in the exercise of the powers conferred on it can be the subject of judicial review or review by another body which is a court or tribunal within the meaning of Article [234 EC] and independent of both the contracting authority and the review body.

The members of such an independent body shall be appointed and leave office under the same conditions as members of the judiciary as regards the authority responsible for their appointment, their period of office, and their removal. At least the President of this independent body shall have the same legal and professional qualifications as members of the judiciary. The independent body shall take its decisions following a procedure in which both sides are heard, and these decisions shall, by means determined by each Member State, be legally binding.’

‘The contracting authority shall, within 15 days of the date on which the request is received, inform any eliminated candidate or tenderer of the reasons for rejection of his application or his tender and any tenderer who has made an admissible tender of the characteristics and relative advantages of the tender selected as well as the name of the successful tenderer.

However, contracting authorities may decide that certain information on the contract award, referred to in the preceding subparagraph, shall be withheld where release of such information would impede law enforcement or otherwise be contrary to the public interest or would prejudice the legitimate commercial interests of particular undertakings, public or private, or might prejudice fair competition between suppliers.’

‘Contracting authorities who have awarded a contract shall make known the result by means of a notice. However, certain information on the contract award may, in certain cases, not be published where release of such information would impede law enforcement or otherwise be contrary to the public interest, would prejudice the legitimate commercial interests of particular enterprises, public or private, or might prejudice fair competition between suppliers.’
‘The contracting authorities shall respect fully the confidential nature of any information furnished by the suppliers.’

National legislation

‘Parties, their advisers and the government commissioner may inspect the case-file at the registry.’
‘Where the defendant fails to lodge the administrative file within the prescribed period, without prejudice to Article 21a, the facts alleged by the applicant shall be deemed to have been proven, unless they are manifestly inaccurate.

Where the administrative file is not in the possession of the defendant, he shall inform the Chamber seised of the action accordingly. The Chamber may order that the administrative file be lodged, on penalty of a fine in accordance with Article 36.’

The dispute in the main proceedings and the question referred for a preliminary ruling

‘Must Article 1(1) of [Directive 89/665], read with Article 15(2) of [Directive 93/36] and Article 6 of [Directive 2004/18], be interpreted as meaning that the authority responsible for the appeal procedures provided for in that article must ensure confidentiality and observance of the business secrets contained in the files communicated to it by the parties to the case, including the contracting authority, whilst at the same time being entitled to apprise itself of such information and take it into consideration?’

Admissibility

Merits

Costs

Operative part

On those grounds, the Court (Third Chamber) hereby rules:

Article 1(1) of Council Directive 89/665/EEC of 21 December 1989 on the coordination of the laws, regulations and administrative provisions relating to the application of review procedures to the award of public supply and public works contracts, as amended by Council Directive 92/50/EEC of 18 June 1992 relating to the coordination of procedures for the award of public service contracts, read in conjunction with Article 15(2) of Council Directive 93/36/EEC of 14 June 1993 coordinating procedures for the award of public supply contracts, as amended by European Parliament and Council Directive 97/52/EC of 13 October 1997, must be interpreted as meaning that the body responsible for the reviews provided for in Article 1(1) must ensure that confidentiality and business secrecy are safeguarded in respect of information contained in files communicated to that body by the parties to an action, particularly by the contracting authority, although it may apprise itself of such information and take it into consideration. It is for that body to decide to what extent and by what process it is appropriate to safeguard the confidentiality and secrecy of that information, having regard to the requirements of effective legal protection and the rights of defence of the parties to the dispute and, in the case of judicial review or a review by another body which is a court or tribunal within the meaning of Article 234 EC, so as to ensure that the proceedings as a whole accord with the right to a fair trial.